Project: nburkholder   -  
            Listing for Category : fuselage
    (Please mouse-over any icon to get a description of that function).


  
Builder Name:Nancy Burkholder   -  
Project:   Vans - RV-9   -   VIEW REPORTS
Total Hours:1181.4
Total Flight Time:
Total Expense:$2.00
Start/Last Date:May 14, 2022 - No Finish Date
 
Friendly URL: https://eaabuilderslog.org?s=nburkholder

Home or Last Project Picture

May 14, 2024     More Canopy Track Attachment - (3 hours)       Category: Fuselage
Fabricate two new spacers to fit under the rear screw holding the canopy rail to the fuselage. The plans call for 1/8" thick shim but 3/16" completely fills the gap nicely. Fabricate two tools to facilitate attaching nuts and washers to the screws that hold the canopy rail to the fuselage. There is a large lip un the underside of the canopy attach stringer that obstructs access to the screw. One tool holds a nut and washer to a fixture that can be inserted into the slot and into position to engage the screw. The second tool provides an offset drive to a socket that allows the socket to engage the nut and the socket drive is offset to pass through the slot. Tried both tools on one screw and they worked acceptably.

Measured and ordered longer rivets and screws to attach the canopy rails and Supertrack rails to the F-705 builkhead assembly.


 
May 13, 2024     Rivet F-705 Bullkhead Assembly to Fuselage - (2 hours) Category: Fuselage
Rivet on left fuselage at junction with F-705 Bullkhead Assembly. Some rivets not set by quickbuild: skin to longeron and longeron toF-705 Bullkhead Assembly. Countersink the canopy slide rail and match drill to fuselage at the forward attach screw. Drill some screw attachments for left and right side canopy roller tracks.
 
May 12, 2024     Rivet F-705 Bullkhead Assembly and Skins to Longeron - (2 hours) Category: Fuselage
Add rivets to right side fuselage at rearF-705 Bullkhead Assembly that were not set by quckbuild: longeron to skin and F-705 Bullkhead Assembly to longeron. Need to order some longer rivets to complete all missing rivets.
 
May 01, 2024     Fabricate Canopy Slider Track - (2.5 hours)       Category: Fuselage
Drill the canopy track spacer for rivet and attach screws. Cut and bend the canopy track rail to fit the spacer. Match drill the rail to the spacer, machine countersink the rivet locations top and bottom, and rivet the rail to the spacer. Cleco the canopy track to the fuselage and verify fit.


 
Apr 30, 2024     Bend Canopy Slide Spacer - (1 hour)       Category: Fuselage
Received RV-8 canopy slide spacer from Vans. The forward bend is not correct for the RV-9. Bend the spacer to match the RV-9 spacer using a c clamp as an mandrel.


 
Apr 30, 2024     Mount Nutplates to Lower Cowl - (1.5 hours)       Category: Fuselage
Mount the upper and lower cowls. Match drill 6 holes for #10 screws attaching the upper and lower cowls behind the propeller spinner. Drill and machine countersink for floating nutplates. Rivet nutplates.


 
Apr 28, 2024     Fasten Aluminum Backing Tabs to Front Lower Cowl - (1 hour)       Category: Fuselage
Match drill the front top and bottom cowl behind the propeller spinner for three screws on the left and right sides. Remove the top cowl and fabricate aluminum tabs to reinforce where nutplates will be mounted for the screws. Epoxy the tabs to left and right side. Remove the lower cowl and set aside to allow the epoxy to cure.


 
Apr 27, 2024     Lower Cowl Skybolts and Rivets - (4 hours)       Category: Fuselage
Remove upper and lower cowl. Using a pneumatic riveter with a very narrow jaw. finish riveting the horizontal cowl lower attach plates for rivets that could not be reached with a stock riveter due to the close clearance between the firewall attach point and the engine mount. Rivet Skybolt receptacles to the flanges on the lower cowl at the vertical firewall joint on the right and left sides. Drill the cowl for grommets, attach grommets, and insert studs. Fit cowl lower and upper cowl. Adjust stud depth for a few studs that were not set for the correct depth. Note the clearance between the lower cowl and the filter air box snorkel. I believe this location is ready for installation of rubber baffling.


 
Apr 24, 2024     Mount Skybolts at Right Cowl Horizontal Split Line - (2.5 hours)       Category: Fuselage
Rivet flanges to lower cowl. Rivet receptacles to flanges. Mark Skybolt hole locations on upper cowl, drill, and attach grommets and studs. Verify cowl fit and adjust several Skybolts for correct depth.


 
Apr 23, 2024     Prepare Skybolt Flanges for Right Cowl Split LIne - (3 hours)       Category: Fuselage
Mount Skybolt flanges to the lower cowl at the right horizontal split line. Match drill the flanges to the cowl. Deburr, machine countersink, and prime the flanges. Machine countersink the lower cowl.


 
Apr 21, 2024     Attach Skybolt Flanges to Lower Cowl Horizontal Split LIne - (3 hours)       Category: Fuselage
Rivet Skybolt flanges to left side of lower cowl at the horizontal split line. Match drill the upper cowl to the Skybolt flanges. Drill upper cowl to accept grommets. Install studs and attach the upper and lower cowl along the left horizontal split line and along the firewall. Pull pins on the receptacles to lock the receptacles in place.


 
Apr 20, 2024     Prepare Skybolts Along Left Horizontal Cowl Split Line - (3 hours)       Category: Fuselage
Mount flanges to the lower cowl along the horizontal split line. Match drill the attaching rivets using a rivet fan. Deburr, machine countersink, and prime flanges. Machine countersink the lower cowl.


 
Apr 20, 2024     Install Skybolts on Upper Cowl at Firewall - (2 hours)       Category: Fuselage
Drill remaining upper cowl at firewall to accept grommets.


 
Apr 19, 2024     Trim Lower Cowl Horizontal Split LIne - (3 hours)       Category: Fuselage
Trim lower cowl horizontal split line. The left horizontal split line has sufficient clearance with the upper cowl. The right horizontal split line needs some additional trimming towards the aft and at the nose.


 
Apr 18, 2024     Trim Upper Cowl and Install Skybolt - (3 hours)       Category: Fuselage
Install 5 Skybolt receptacles and grommets. Trim the upper cowl horizontal split line.


 
Apr 15, 2024     Upper Cowl Oil Door - (2 hours)       Category: Fuselage
Cut out oil door in upper cowl. Attach upper cowl to firewall fuselage with Skybolt cleco adapters. Identify trimming of the upper fuselage and verify vertical placement of the horizontal Skybolt flanges on the right side.


 
Apr 14, 2024     Lower Cowl Attachment - (3 hours)       Category: Fuselage
Rivet lower cowl attachment plates to fuselage and match drill plate nuts to cowl. Not all rivets set due to not having a suitable bucking bar for close clearance with engine mount. Match drill lower cowl right vertical Skybolt cleco adapters to cowl.


 
Apr 13, 2024     Lower Cowl Fuselage Attachment - (5 hours)       Category: Fuselage
Fabricate two lower cowl bottom attach plates. Apply primer and ready to rivet to fuselage. Rivet the right side lower cowl flanges to the fuselage.


 
Apr 12, 2024     Fitting Cowl with Skybolts - (5 hours)       Category: Fuselage
Match drill the remaining upper cowl Skybotts to the bushings in the flanges. Fit the lower cowl and match drill the side Skybolts to the bushings mounted in the flanges.


 
Apr 05, 2024     Drill Locating Holes for Cowl Skybolt Studs - (6 hours)       Category: Fuselage
Sand and apply second layer of epoxy with filler to the outside lower cowl exhaust outlet. Mount Skybolt flanges to upper cowl firewall. Tape 10 Skybolt cleco drill bushings to the flanges working from the center flange to the left and right side. Place and level upper cowl. From under the cowl shine a flashlight through each cleco drill bushing hole and mark the light spot seen on the outside of the cowl. Drill #40 and then #30 to align the cowl hole with the hole in the busing. Drill 13 of 17 upper firewall Skybolt flanges.


 
Mar 30, 2024     Prime Skybolt Flanges - (3 hours)       Category: Fuselage
Scuff Skybolt flange surfaces with Scotch Brite pads, wipe with MEK cloth, and apply primer to the flanges. Apply Proseal to the left and right vertical firewall seams with the fuselage skin.


 
Mar 24, 2024     Mount Lower Cowl Vertical Skybolt Flanges - (3 hours)       Category: Fuselage
Lay out the location for Skybolt fasteners on the left and right lower cowl vertical firewall attach points, clamp the flanges to the fuselage, and match drill to the vertical firewall rivet locations. Remove the flanges, deburr drilled holes, machine countersink the rivet attach holes and the Skybolt fastener holes, and remount the flanges to the vertical firewall.


 
Mar 24, 2024     Supertracks Rear Mount - (2.5 hours)       Category: Fuselage
Fabricate two threaded spacers to support the aft ends of the Supertracks. Fabricate the spacers from 1/2" aluminum bar stock. Use metal lathe to cut spacers slightly long and then face off the ends flat to the desired length. Center drill the spacers and tap for 10-32 threads.


 
Mar 23, 2024     Prepare Upper Cowl Skybolt Flanges - (5 hours)       Category: Fuselage
Verify fuselage level orientation. Determine approximate horizontal cowl split line. Lay out Skybolt flange locations on upper firewall. Mount and drill Skybolt flanges to the firewall upper cowl. Remove, deburr, machine countersink, and remount flanges flanges.


 
Mar 22, 2024     Trim and Fit Upper and Lower Cowl - (4 hours)       Category: Fuselage
Mount lower and upper cowl and trim lower cowl to fit. Mount top cowl, mark spots that need trimming, remove cowl, trim, and remount. Repeat until the cowl fits reasonably well. Begin working through how to mount the Skybolt flanges.


 
Mar 19, 2024     Mount Super Tracks, Lower Cowl - (4 hours)       Category: Fuselage
Apply second layer of fiberglass to lower engine cowl exhaust exit. Drill Super Tracks mounting holes and fabricate four shims. Fabricate tool to enable machine countersinking the forward mounting screw. Match drill the Super Tracks to the fuselage.


 
Mar 17, 2024     Canopy Preparation - (6 hours)       Category: Fuselage
Clamp the sliding canopy track to the longerons and match drill the outer mounting holes. Made a decision to incorporate the Fly Boy's Super Tracks to the canopy build now. Rivet the canopy track extension to the stock track. Notch the canopy tracks at the aft top to allow the canopy rollers to exit the canopy track when sliding the canopy open. Fit the right Super Track in position and bevel the aft end to nestle next to the rear skin.


 
Mar 17, 2024     Remove Cowl Pipe Mold - (.5 hour)       Category: Fuselage
Remove the mold used to form the exhaust pipe exit on the lower cowl. Trim the stray fibers and excess fiberglass at the exit.


 
Mar 16, 2024     Fiberglass Cowling At Exhaust Pipe Exit - (1.5 hours)       Category: Fuselage
Create a mold from a large can wrapped with packing tape. Fit mold to lower cowling with fiber glass mat in place. Cover mat with epoxy resin.


 
Mar 15, 2024     Final Cowl Trim - (4 hours)       Category: Fuselage
Trim upper and lower cowl to exact firewall clearance. The top cowling ended up with gaps that will need to be filled and shaped. The bottom cowl came out precise with only some light sanding. Cut the clearance relief for the exhaust pipe exit. The cut is ready for fiber glassing the cowling exit channel covering the exhaust pipe.


 
Mar 14, 2024     Trim Cowl at Firewall - (3 hours)       Category: Fuselage
Trim upper and lower cowl at the firewall. This is an initial trim that still needs to be precisely matched to the firewall. Verify cowls are level.


 
Mar 13, 2024     Canopy Cowl trim lines - (1 hour) Category: Fuselage
Mark firewall trim lines for upper and lower cowling.
 
Mar 12, 2024     Cleco Cowling to Fuselage - (2 hours)       Category: Fuselage
Add temporary mounting flanges to firewall. Mount cowling, match drill cowling to temporary flanges, and cleco the cowling to the temporary flanges.


 
Mar 08, 2024     Preliminary Cowling Fit - (3 hours)       Category: Fuselage
Clamp cowling to fuselage and establish the horizontal and vertical placement using a laser level. Mount propeller spinner backplate to propeller and measure distance from propeller mounting flange to rear of spinner.


 
Mar 02, 2024     More Cowl to Prop Spinner Clearance Adventures - (2 hours)       Category: Fuselage
Reviewing my prior measurement of the distance from propeller aft mounting/crankshaft flange to the spinner backing plate I mounted the plate backwards. The spinner backing plate has a 5/8" flange around the circumference for mounting nut plate attaching the spinner. This flange extends 7/16" aft from the aft backing plate mounting surface; 5/8" flange - 1/16" spinner back plate thickness - 1/16" spinner backing plate doubler). The location of the cowl relative to the crankshaft mounting is as follows. 1/4" flywheel thickness, 2" from the propeller aft mounting surface to the spinner backing plate minus 7/16" lip. Set Ez Cowl jig for 1 9/16". This distance is less than the supplied spacer that I used to set the clearance distance. Replace the spacer with the four bolts and locking nuts that hold the jig to the flange. The forward bolt head surface sets the clearance distance. The 1-1/4" bolts I have on hand are barely long enough and 1-3/4" bolts on order.


 
Mar 01, 2024     Trim Lower Cowl - (2 hours)       Category: Fuselage
Trim the lower cowl to fit around gear legs.


 
Feb 29, 2024     Attach Nose Bowl Plate to Cowl - (2 hours)       Category: Fuselage
Determine that the fuselage longerons leveled horizontally are the desired position for mounting the cowl. The engine crank with the attached Ez Cowl Jig is also horizontal. Horizontally center the nose bowl plate on the cowl nose bowl. Vertical center the nose bowl plate and then raise the plate about 1/8" to account for engine mount sag. Match drill and cleco the nose bowl plate to the cowl nose bowl. Place the upper and lower cowl on the Ex Cowl Jig and slide it aft until the lower cowl touches the landing gear legs.


 
Feb 26, 2024     More Cowl Preparaton - (4 hours)       Category: Fuselage
Fabricate a Lexan nose bowl disk to replace the OSB disk. It's thinner and can be clecoed to the cowl. Raise the tail with a longer upright to get the longerons level. This leveled the rear longeron but upon further consideration I probably want to level the forward longeron. Added center lines to the upper and lower cowl. Modified a rubber plug inserted into the crankshaft to block moisture. The plug was initially slightly too small for a tight fit so I expanded it using a 2" socket as a mandrel and a heat gun. Then I trimmer the outer diameter to the same size as the crank OD. Attached the David Howe Ez Cowl Jig to the crank prop flange.


 
Feb 24, 2024     Cowl Preparation - (3 hours)       Category: Fuselage
Complete research and order Skybolt fasteners for the cowling. Cleco the forward top fuselage skin. Add reference line 2" aft of the firewall in preparation for fitting the cowl. Pilot drill #40 the forward cowl attach screws.


 
Feb 23, 2024     Fitting Engine Cowl - (3 hours)       Category: Fuselage
Grind and fit the flanges mating the upper and lower cowl at the nose bowl.


 
Oct 29, 2023     Mount Com Antenna - (1 hour)       Category: Fuselage
Mount the Com antenna. I may rivet the doubler plate to the fuselage to facilitate future maintenance.


 
Oct 28, 2023     Antenna and Cable Infrastructure - (5 hours)       Category: Fuselage
Mount 5 lug terminal strip to the fuselage on the right near the right wing attach point. This strip will splice the CAN bus to the roll servo and the autopilot disconnect wire. Permanently mount the ADS-B receiver mounting brackets to the forward fuselage. Fabricate a doubler plate for mounting the COM antenna to the bottom fuselage aft of the baggage compartment.


 
Oct 27, 2023     tid bits - (2 hours)       Category: Fuselage
Fabricate a bracket to hold a 5 lug terminal strip. Add zip tie mounts to fuselage to route GPS and ELT antenna cables.


 
Oct 23, 2023     Add conduit - (2 hours)       Category: Fuselage
Add conduit to route GPS and Com coax cables from center fuselage on right to behind the baggage compartment bulkhead.


 
Oct 22, 2023     Rivet Doubler Plates to fuselage - (2 hours)       Category: Fuselage
Dimple fuselage at GPS and ELT doubler plates. With assistance rivet doubler plates to fuselage.


 
Oct 21, 2023     GPS & ELT antenna doubler plates - (5 hours)       Category: Fuselage
Fabricate GPS and ELT antenna doubler plates. Match drill fuselage for both plates.


 
Oct 13, 2023     Rivet subpanel and instrument panel - (4 hours)       Category: Fuselage
Complete riveting the instrument panel and subpanel to the fuselage.


 
Oct 01, 2023     Rivet subpanels - (2 hours)       Category: Fuselage
Continue riveting forward fuselage subpanels.


 
Sep 26, 2023     Complete installing AHRS doubler plate - (2 hours)       Category: Fuselage
Install nut plates and rivet AHRS doubler mounting plate to subpanel


 
Sep 24, 2023     Fuselage Modifications - (8 hours)       Category: Fuselage
Move left and right wing wiring terminal blocks to inside of rib to allow full access to the outer bay when installing wing attachment bolts. Make doubler plate to attach ADHARS to subpanel. This location facilitates the display screen removal. Move sensor manifold attachment to firewall to a vertical alignment in line with center forward fuselage rib. This location is structurally stronger. Add terminal block to splice sensor wires to the leads from the GEA 24 EMS.


 
Sep 16, 2023     Subpanel fabrication and current shunt - (6 hours)       Category: Fuselage
Begin riveting the forward fuselage subpanel. Add nutplates for mounting the primary fuse block. Fabricate bracket to hold the primary power shunt and sensor wire fuse blocks.


 
Jul 19, 2023     Fitting canopy frame - (8 hours) Category: Fuselage
Starting on July 15, worked several hours per day reading the instructions for fitting the canopy side frames to the longerons and fitting the frame. Completed fitting today. Checked rear bow fit with aft turtledeck skin with the bow below the skin by 1/8 to 5/8". Checked front bow with roll bar. Front bow 1/4 to 3/4" higher than roll bar. Will consider trimming the front bows where the rollers attach after fitting the canopy bubble.
 
Jul 14, 2023     Fit sliding canopy frame to fuselage - (8 hours)       Category: Fuselage
Cut and drill canopy slide rails. Fabricate center canopy guide. Temporarily mount slide rails and canopy guide to fuselage and begin fitting the canopy sliding frame.


 
Jul 09, 2023     Attach Roll Bar - (8 hours)       Category: Fuselage
Fabricate attachment shims, lay out roll bar attach points. Drill fuselage roll bar attach points and bolt roll bar to fuselage. Trim roll bar brace, match drill, and bolt brace to roll bar and fuselage.


 
Jul 07, 2023     Add subpanel supports for avionics and control cables - (4 hours)       Category: Fuselage
Created subpanel supports for the avionics stack and control cables. The control cables will be attached with Adel clamps.


 
Jul 02, 2023     Attach stick grips - (2 hours)       Category: Fuselage
Attach pilot and copilot stick grips to control sticks. Trim both sticks to eliminate interference with instrument panel controls.


 
Jul 01, 2023     Test fit panel - (4 hours)       Category: Fuselage
Cleco upper deck spars and subpanels,and mount panel in fuselage to test fit wiring with cutout hole in subpanel. Organize wiring routed from aft into two bundles that will route to the panel along the floor to the forward uprights, one on the left and the other on the right


 
May 28, 2023     Mount Alternate Air Door cable pass through - (2 hours)       Category: Fuselage
Drill firewall for alternate air door firewall pass through fitting. Tight space between mounted throttle fitting and vertical angle brace. Trim edge of throttle firewall pass through fitting and starter solenoid mounting bracket reinforcement plate to accommodate pass through fixture.


 
May 28, 2023     Fabricate secondary battery hold down strap - (3.5 hours)       Category: Fuselage
Fabricate hold down strap for secondary battery. Scuff and prime strap. Removable by pulling hinge pins.


 
May 21, 2023     Complete match drilling forward top skin - (4 hours)       Category: Fuselage
Clamp forward upper fuselage skin to workbench and roll form it around a pipe to add bend. Cleco and match drill the forward upper fuselage skins to fuselage and firewall..


 
May 19, 2023     Test fit forward upper fuselage skin - (1 hour)       Category: Fuselage
Cleco forward upper fuselage skin to fuselage in preparation for match drilling and dimpling to airframe and identify precise instrument panel location prior to drilling holes for panel to fuselage mounting angles.


 
May 18, 2023     Replace right wing vent line - (2 hours)       Category: Fuselage
Right wing fuel tank vent line interfered with subpanel. Fabricate new vent line fitted to avoid interference.


 
May 14, 2023     Replace left wing tank vent line - (2 hours)       Category: Fuselage
Original left wing vent line interfered with subpanel. Fabricate and install new vent line.


 
May 01, 2023     Prepare flap and aileron gap seals - (4 hours) Category: Fuselage
Match drill, dimple, and prime right wing aileron and flap gap seals.
 
Apr 28, 2023     Complete aft top skin riveting - (2 hours)       Category: Fuselage
Complete riveting the aft top skin at and forward from the baggage compartment bulkhead.


 
Apr 27, 2023     Rivet aft top fuselage skin - (4 hours)       Category: Fuselage
Cleco aft top skin to fuselage and rivet to fuselage except for rivets at and forward from the baggage compartment bulkhead.


 
Apr 25, 2023     Horizontal Stabilizer trim pieces - (3 hours)       Category: Fuselage
Fit horizontal stabilizer trim pieces to fuselage. Match drill and dimple trim to fuselage holes. Trim about 1/16" to create a gap between the trim piece and HS.


 
Apr 23, 2023     Rudder pedal brake lines - (2 hours)       Category: Fuselage
Install fittings to brake cylinders. Cut for fit the left and right brake lines. Check for fit in fuselage.


 
Apr 22, 2023     Fabricate battery box and drill firewall penetrations - (8 hours)       Category: Fuselage
Started on 4/21 and finishing today. Fabricate battery box and install on firewall. Create steel template for drilling fire wall penetrations for DoubleTee firewall fittings. Locate and drill throttle, mixture, and propeller governor fittings and install on firewall.


 
Apr 16, 2023     Paint fuselage interiorq - (2 hours)       Category: Fuselage
Mask and cover fuselage in preparation for painting. Wipe all surfaces to be painted with coarse Scotch Brite pad and wipe with tack cloth. Hired painter to paint the fuselage interior. Jeff did a fabulous job.


 
Apr 11, 2023     Pick up removable interior panels from paint shop - (2 hours)       Category: Fuselage
Inventory and transport 30 removable panels, flooring, and seat backs to paint shop. Pick up painted parts.


 
Apr 08, 2023     Attach fuel senders to mounting plate - (6 hours)       Category: Fuselage
Attach fuel senders with cork gaskets to fuel line mounting plates. Kit inventory provided two left tank sending units 385B. Install the right sending unit upside down. Bend float rods and install on senders. Attach right sender to left tank and left sender to right tank with floats facing outside. Verify float travel from minimum to maximum travel.


 
Apr 08, 2023     Mount light control board - (6 hours)       Category: Fuselage
Fabricate mounting bracket for FlyLEDS "works" control circuit board. Attach bracket to fuselage.


 
Mar 30, 2023     Fuel selector valve and lines - (4 hours)       Category: Fuselage
Mount fuel selector valve to valve mounting plate. Fit left and right fuel tank lines from the valve to outboard the fuselage. Temporary installation without flare fittings which will be added at final installation after installing the fuel filter and boost pump.


 
Mar 25, 2023     Collect panels for painter - (2 hours)       Category: Fuselage
Collect all removable panels and cabin artifacts needing painting, label and catalog them prior to sending to the painter. Thirty items total.


 
Mar 25, 2023     Fabricate stick boot rings - (2 hours)       Category: Fuselage
Fabricate two stick boot rings.


 
Mar 25, 2023     Fabricate and install left fuel tank vent line - (3 hours)       Category: Fuselage
Fabricate and install left fuel tank vent line


 
Mar 24, 2023     Right Fuel Tank Vent Line - (4 hours)       Category: Fuselage
Fabricate and install the right fuel tank vent line.


 
Mar 19, 2023     Wiring for ELT and Pitch Servo - (4 hours)       Category: Fuselage
Route wiring from the empennage forward towards the pitch servo. Connect pitch servo wiring and route the wiring forward through the center tunnel. Wire the ELT except for the antenna, and run wiring forward through the center tunnel.


 
Mar 18, 2023     ELT and Mag Sensor - (10 hours)       Category: Fuselage
Complete wiring the magnetometer connector. Fabricate a mounting plate for the ELT. Mount ELT to fuselage.


 
Mar 17, 2023     Wiring to Tail Light and Conduit to empennage - (8 hours)       Category: Fuselage
Install conduit to carry wiring from the empennage forward to behind the baggage comparment. Install wiring tail light forward to the fuselage behind the baggage compartment. Rivet the rudder fairing.


 
Mar 15, 2023     Tail light wiring - (4 hours)       Category: Fuselage
Add conduit to bottom of rudder tip. Drill hole through vertical stabilizer for tail light wire. Attach rudder to vertical stabilizer. Route tail light wire from empennage to tail light.


 
Mar 13, 2023     Routing static line - (4 hours)       Category: Fuselage
Routed conduit along left side under the baggage floor and seat floor. Add cable ties to support static line leading to the conduit.


 
Mar 11, 2023     Flaps and Static Port - (10 hours)       Category: Fuselage
Assembled flap mounting, added nut plates, and fit the side skirts. Mounted two static ports and routed line to the lower fuselage.


 
Mar 10, 2023     Flap attach bracket - (6.7 hours)       Category: Fuselage
Make angles and plates for flap assembly. Fit bracket to fuselage and match drill. Attach flap motor to bracket and actuator. Rivet all flap bracket parts and nut plates. Attach nut plates to forward elevator push tube tunnel.


 
Mar 06, 2023     Install flap actuator - (4 hours)       Category: Fuselage
Cut and drill 3 flap bearing blocks and install flap actuator in fuselage. Drill safety wire hole in the end of flap motor shaft.


 
Mar 05, 2023     Create carboard templates - (3 hours)       Category: Fuselage
Create cardboard templates for fuselage floor and side walls.


 
Mar 04, 2023     Begin empennage wiring - (5 hours) Category: Fuselage
Install electric trim servo and wiring in elevator. Route wiring to rear bulkhead. Run rear tail light and strobe through empennage. Reinstall vertical stabilizer.
 
Mar 04, 2023     Install heat vent valve - (5 hours)       Category: Fuselage
Drill two 2" holes in firewall for heat valve. Use 2" hole saw and a piece of wood with 2" hole to prevent the hole saw center from wandering. Use slow speed, plenty of cutting oil, and constant pressure. Bend center cover air louvers. Clamp a stiff straight edge to the bend line and a wide putty knife inserted under the louver as a metal brake.


 
Feb 24, 2023     Instrument panel layout - (10 hours)       Category: Fuselage
Working with UpNorth Aviation for the past month laying out the instrument panel. The panel is ready to cut out.


 
Feb 19, 2023     Install control sticks - (4 hours)       Category: Fuselage
Install left and right control sticks.


 
Feb 12, 2023     Aileron Trim - (5 hours)       Category: Fuselage
Fabricate aileron trim control and mount.


 
Feb 11, 2023     Attach fresh air intakes - (4 hours)       Category: Fuselage
Install fresh air intakes to fuselage


 
Feb 04, 2023     Steps and Brake Reservior - (3 hours)       Category: Fuselage
Drill firewall, attach nut plates, and brake reservoir to firewall. Rivet left and right steps with help from Xander.


 
Jan 23, 2023     Install Pitch Servo - (2 hours)       Category: Fuselage
Rivet pitch servo mount to center skin brace. Attach pitch servo to elevator bell crank.


 
Jan 21, 2023     Install Roll servo, HS tips - (4 hours)       Category: Fuselage
Rivet the horizontal stabilizer fiberglass tips. Install the roll servo in the right wing.


 
Jan 11, 2023     Inventory Finishing Kit - (3 hours) Category: Fuselage
Received finishing kit yesterday. Inventory complete except for back ordered items.
 
Jan 01, 2023     Match drill panel angles - (4 hours)       Category: Fuselage
Add nut plates and cleco attach angles between panel and fuselage. This is a temporary setup before committing to using the supplied panel. Cleco the angle joining the center rib with the middle subpanel.


 
Dec 31, 2022     Attach rudder pedals to rudder pedal assembly - (1 hour) Category: Fuselage
Attach 4 rudder pedals to the rudder pedal assembly.
 
Dec 31, 2022     Fit front deck - (6 hours)       Category: Fuselage
Make attach angles, plate, and stiffening angle. Drill center rib to firewall. Deburr and fit left, center, and right ribs, left and right outboard subpanels, and center subpanel to fuselage. Check partial fit of forward top skin to verify fit with center rib.


 
Dec 18, 2022     Mainly Crotch Straps and VS tip - (7 hours)       Category: Fuselage
Drill to fuselage, deburr, install nut plates, and primer right and left crotch straps. Ready for riveting. Create a fiberglass 4 ply layup sheet to enclose the aft end of the vertical stabilizer tip. Cut and shape to fit inside tip. Trim rudder lower fiberglass tip to fit around rudder cable attach brackets. Drill rivet holes tip to lower rudder. Drill mounting hole for rear marker light/strobe.


 
Dec 11, 2022     Mount Rudder to VS, install tail cone stiffeners - (6 hours)       Category: Fuselage
Mount Rudder to Vertical Stabilizer. File rudder stops to ensure 35 degree rudder deflection. Measured 46 1/8" from rudder trailing edge to outboard elevator trailing edge. Unbolt HS and VS from fuselage and deburr all mounting holes. Install left and right rear tail cone stiffeners F-00773A: Look up installation on Van's website because drawings did not show, layout on fuselage, drill, dimple, and rivet stiffeners to fuselage.


 
Dec 11, 2022     Mount steps to fuselage - (1.3 hours)       Category: Fuselage
Cleco left and right steps to fuselage and bolts support blocks and steps to fuselage. Ready to rivet steps.


 
Dec 10, 2022     Drill Rear VS Spar to bulkhead - (2 hours) Category: Fuselage
Drill vertical stabilizer rear spar to rear bulkhead F-712.
 
Dec 08, 2022     Drill horizontal and vertical stabilizer to fuselage - (2 hours)       Category: Fuselage
Drill vertical stabilizer front spar to F-981 attach plate. Drill horizontal stabilizer rear spar to Up elevator stop F-912C.


 
Dec 07, 2022     Mount horizontal and vertical stabilizer to fuselage - (2 hours) Category: Fuselage
Fabricate and mount Up Elevator Stop F-912. Mount attach plate F-981 to horizontal stabilizer forward spar. Trim vertical stabilizer forward spar Clamp the vertical stabilizer rear spar to to the back of builkhead F-912. Adjust vertical stabilizer such that the hinge line is colinear.
 
Dec 05, 2022     Steps and Vertical Stabilizeer - (4 hours) Category: Fuselage
Drill left step support block and deburr step. Prime left and right step. Restore the F-750R,L rear baggage cover plate nuts to the bulkhead. Both steps ready for permanent installation.

Bolt F-981 attach plate to horizontal stabilizer forward spar. Trim VS-702 vertical stabilizer forward spar as depicted in DWG 27A. Fabricate elevator stop F-912D.
 
Dec 03, 2022     Mount Left Step - (8 hours)       Category: Fuselage
Complete drilling left step support block to floor rib. Drill 1 1/2" diameter holes through skin and two ribs, and trim two flanges to situate the step to the left fuselage. Remove F-650 rear side baggage cover; drilled out QB installed nutplates, to expose F-624 rib that will support riveting the step to the fuselage. Drill left step rivet and support blocks. Left and right step ready for priming and riveting.


 
Dec 02, 2022     Start Right Step Mount - (3.3 hours)       Category: Fuselage
Drill 1 1/2" diameter holes through skin and two ribs, and trim two flanges to situate the step to the right fuselage. Remove F-650 rear side baggage cover; drilled out QB installed nutplates, to expose F-624 rib that will support riveting the step to the fuselage.


 
Nov 12, 2022     Rivet rear bulkhead and rudder stops - (7 hours)       Category: Fuselage
Rivet rear bulkhead F-712 to fuselage except for lower, inside rivets. Need pull rivets. Rivet rudder stops to fuselage. Add lightening holes to rudder pedal brace F-6118. Drill 3rd rudder position position. Split side rudder pedal bearing blocks. Since steps and flap parts are on back order, the next step appears to temporarily mount the wings and set the wing incidence.


 
Nov 10, 2022     Forward covers - (5 hours)       Category: Fuselage
Fit center floor F-982C, access plate F-982E, and heat baffle F-982C, and install nut plates and rivet. Rivet nut plates to fuel valve plate V-983A and screw to bulkhead F-904. Fit F-982C between center floor reinforcement angles and adjust to fit fuel valve cover F-983C. Drill F-982C to floor stiffener angles and firewall recess F-601K-1. Install all remaining nut plates. Do not trim fuel valve cover yet.


 
Nov 09, 2022     Seat backs and rests - (4 hours)       Category: Fuselage
Rivet right and left seat backs and seat back braces. Add lightening holes to seat back braces. Match drill and dimple F-982E access plate and F-982 heat baffle to F-982C center cabin cover. Cleco nut plates to F-982C.


 
Nov 08, 2022     Seat backs and rests - (4 hours) Category: Fuselage
Rivet right and left seat backs. Fabricate two seat back rests; ready for riveting and lightening holes.
 
Nov 07, 2022     Build right seat back - (3 hours) Category: Fuselage
Drill, deburr, and prime right seat back assembly. Ready for riveting.
 
Nov 06, 2022     Tunnel cover & seat backs - (10 hours)       Category: Fuselage
Riveted tunnel cover to side flanges and drilled to forward floor and attached nut plate. Completed preparing left seat; material cut, drilled, and deburred. Started right seat.


 
Nov 03, 2022     Harness cable wear blocks - (4 hours) Category: Fuselage
Fabricate parts and install F-6114B&C cable wear blocks.
 
Nov 02, 2022     Baggage Compartment - (3.5 hours) Category: Fuselage
Drill in place the forward top skin F-774 to bulkheads and stringers. Skip steps installing the steps which are back ordered. Install nutplates on F-706
 
Oct 30, 2022     Fitting forward top skin and F-6111 ribs - (5 hours)       Category: Fuselage
Fit the F-7112 forward top skin to F-706 and F-707 bulkheads. Fit F-788 gusset. Ready to drill skin to bulkheads, stringers, and gussets. Trim and match drill F-6111 ribs to F-7112 skin.


 
Oct 30, 2022     Fabricate and fit elevator bell crank - (2.5 hours) Category: Fuselage
Trim F-757 gussets per plan Assemble and install elevator bell crank. Remove and store for use later. Quick build verify bell crank support, fitting aft top skin, and installing F-565L and R gusset plates.
 
Oct 29, 2022     Mount Rudder pedals in fuselage - (5 hours)       Category: Fuselage
Drill mounting holes in rudder pedal end blocks and center support block. Cut center support block per drawing. Mount rudder pedals in fuselage and drill mounting holes 3" from firewall. Cut and drill rudder pedal support bracket and match drill for mounting to firewall. Drill support bracket to fit center support block. Inspect quick build fuselage steps: install floor stiffeners, framing baggage area, riveting forward side skins, finishing forward fuselage and longeron details, installing forward fuselage gussets, and installing should harness anchors. Mark side gussets F-757 to trim for cutout per drawing.


 
Oct 25, 2022     Rivet rudder pedals - (4 hours) Category: Fuselage
Machine counter sink and rivet left seat right and left rudder pedals.
 
Oct 23, 2022     Fuselage - (8 hours)       Category: Fuselage
Fabricate left and right F-792 rudder stops. Paint WD-409 tail spring bracket; ready to install. Fabricate left rudder pedal; ready to rivet. Inspected fuselage related to preparing and assembling the center fuselage and note instructions for preparing the step for installation (steps are back ordered), joining rear and center fuselage assemblies, adding the forward fuselage, installing auxiliary longerons and forward bulkheads.


 
Oct 22, 2022     Rivet Seat Adjustment Parts - (2 hours) Category: Fuselage
Bend seat adjustment plates with 4 degree bend per drawing. Rivet F-705J angle, F-705K plate, and F-705L seat adjustment supports to F-705F channel for right and left seats.
 
Oct 15, 2022     Drill WD-409 keeper rivet holes - (3 hours) Category: Fuselage
Fit F-712 bulkhead and drill two rivet keeper holes through F-712 and WD-409
 
Oct 14, 2022     Begin WD-409 installation - (4.5 hours) Category: Fuselage
Relieve F-779 skin to make room for tail wheel spring mount tube. Match drill WD-409 to F-711
 
Oct 13, 2022     Inspect Bulkheads - (3 hours) Category: Fuselage
Deburr, machine countersink, and prime seat adjustment parts. Need to bend F-705K with 4 degree angle prior to riveting to fuselage. Inspect quick build bulkheads F706, F-707, F-708, F-709, F-710, F-711, and F-712. Remove F-712 bulkhead and review WD-409 tail wheel spring mount installation.
 
Oct 12, 2022     Seatback fabrication - (4 hours) Category: Fuselage
Fabricate two each F-705J, F705K, and F-705-l seat adjustment supports Inspect F-705 bulkhead construction.
 
Oct 10, 2022     Assembling F-904 Bulkhead - (1.5 hours) Category: Fuselage
Verify quick build assembly: F-904A,B,C,D snap bushing holes 5/8", F-904C-L&R bulkhead assembly, rivet F-904C, F-904D, and F-904G. Fit WD-610, WD-611, and WD-612; filed WD-610, W-D612, and both brass bearings to fit WD-611,
 
Oct 09, 2022     Assemble F-601 Firewall - (6.5 hours) Category: Fuselage
Step through F-601 firewall assembly instructions to verify quick build construction and familiarize with parts, and drawings, Fabricate F-601 TD brake line bracket, match drill, machine countersink, prime, and rivet to firewall. Drill two 7/16" holes through bracket and firewall for brake line fittings, Match drill and dimple firewall recess F-601K-1.
 
Oct 07, 2022     Inventory Fuselage and Wings - (5 hours) Category: Fuselage
Receive quick build wings and fuselage, Store parts in hangar and begin inventory,
 