Project: ranss19   -  
            Listing for Category : brakes
    (Please mouse-over any icon to get a description of that function).



Categories
  
Builder Name:Ken Jordan   -  
Project:   Rans - S-19 Venterra   -   VIEW REPORTS
Total Hours:3
Total Flight Time:
Start/Last Date:Jan 06, 2012 - Aug 02, 2015
Engine:Lycoming IO233
Propeller:Sensenich
Panel:Dynon Skyview; Garmin 430
 
Friendly URL: https://eaabuilderslog.org?s=ranss19

Home or Last Project Picture

May 15, 2020     Parking Brake       Category: Brakes
Removed the factory cable driven linkage to the parking brake. Installed rigid rod driven linkage.


 
Aug 26, 2014     Attached and riveted the right front skin Category: Brakes
Attached and riveted the right front skin. Finished running the brake lines and filled the system with hydraulic fluid and bled the system.
 
Aug 25, 2014     Lines       Category: Brakes
Tried to update the Dynon software to version 11, but it wouldn't let us do that without having the servos attached to the network and we're still waiting for the correct caps for the plugs. We did update maps and terrain. Attached the left front skin and riveted. Started running the brake lines.


 
Jul 07, 2014     Installed parking cable and secured       Category: Brakes
Installed parking cable and secured. Ran cabin heat knob through panel


 
Apr 21, 2014     Brakes assembly       Category: Brakes
Installed brake cylinders, reservoir, and parking brake valve and guide.


 
Dec 21, 2013     Ran the brake fluid lines.       Category: Brakes
Ran the brake fluid lines.


 


NOTE: This information is strictly used for the EAA Builders Log project within the EAA organization.     -     Policy     -     © Copyright 2024 Brevard Web Pro, Inc.