Project: ranss19   -  
            Listing for Category : empennage
    (Please mouse-over any icon to get a description of that function).



Categories
  
Builder Name:Ken Jordan   -  
Project:   Rans - S-19 Venterra   -   VIEW REPORTS
Total Hours:3
Total Flight Time:
Start/Last Date:Jan 06, 2012 - Aug 02, 2015
Engine:Lycoming IO233
Propeller:Sensenich
Panel:Dynon Skyview; Garmin 430
 
Friendly URL: https://eaabuilderslog.org?s=ranss19

Home or Last Project Picture

Jun 23, 2014     Tidied up the cables and lines in the tailcone       Category: Empennage
Tidied up the cables and lines in the tailcone


 
Jan 10, 2012     Flange Bushings Category: Empennage
Put in flange bushings - doing it with the nut and bolt worked, but the bolt was stuck pretty tightly in the bushings. Clecoed the lower ribs to the front spar of the vertical stabilizer
 
Jan 07, 2012     Unpacked and inventoried the contents of the kit       Category: Empennage
Unpacked and inventoried the contents of the kit. Long pieces went out on the lanai. Bought hanging bins to hold the small stuff - rivets, washers, clecos, etc. and stapled the rest in priority number order to the cover of the crate. Taped the supplied labels to the front of each bin. Broke up the rest of the crate and took it to the recycling center.


 
Jan 06, 2012     The empennage kit arrived today       Category: Empennage
The empennage kit arrived today. We took the lid off and made sure everything looked OK


 